Order winNotableFiled on BSE ·

L&T Energy CarbonLite Solutions Secures LNTP for 1,600 MW Chandrapura Thermal Plant

Larsen & Toubro · Construction

What the filing says

  • LNTP received from DVC CIL Power Private Ltd for 2x800 MW ultra-supercritical units in Jharkhand
  • Scope includes design, engineering, manufacturing, supply, erection, testing, and commissioning of boilers, turbines, generators, ESPs, and related works
  • Order classified as Major (₹5,000 to 10,000 crore), with Notice to Proceed pending environmental clearances and LNTP completion

Why it's rated notable: The filing gives an LNTP for a Major order (lower bound ₹5,000 crore, ₹500 crore or more is at least medium, about 1.7% of ₹290,137 crore annual revenue), but the full Notice to Proceed depends on environmental clearances, so the event is not binding and cannot be rated high.

Original filing

Announcement under Regulation 30 (LODR)-Award_of_Order_Receipt_of_Order

Read the filing on BSE (PDF) →

Companies guiding to strong growth

Ranked by management's own guidance on revenue and margins — not by us.

Waaree Energies Ltd

Electrical Equipment

Revenue growth 40%+Margin up 2%+

Sign up free to see all 6 →

See full rankings

Rank buckets describe management commentary on revenue and margin. Not investment advice, and not a forecast of returns.

More from Larsen & Toubro

Other order win filings this fortnight

All order win filings →

Summary written by Arthneeti from the company's filing with the stock exchange; check the original filing for full details. Arthneeti is a research and analytics platform, not a SEBI-registered investment adviser, and nothing here is a recommendation to buy or sell.