Rajesh Power Services Ltd Q3 FY26 Results & Concall Highlights: Revenue, Margins & Order Book
Published 15 Jul 2026 | Other Utilities | Market Cap: ₹1.5K Cr
Rajesh Power Services Ltd. Rajesh Power Services Ltd.
From Rajesh Power Services Ltd's Q3 FY26 earnings-call transcript · updated 23 Aug 2026.
Price
₹831
Market Cap
₹1.5K Cr
P/E Ratio
10.9
How does Rajesh Power Services Ltd rank in Other Utilities?
Compare Rajesh Power Services Ltd against every Other Utilities company this quarter on revenue, margins and earnings-call signals.
📊 Revenue & Sales Performance
- →Rajesh Power Services Ltd. is targeting a revenue CAGR of approximately 40% over the next 2 to 3 years.
- →The company aims to achieve 40% growth specifically in FY27, maintaining a consistent growth trajectory.
- →Order inflows are targeted at INR 4,000 to INR 5,000 crores annually in the near term, with similar levels expected in FY28.
- →The company plans to expand beyond its strong Gujarat market presence (currently 85%-90% of order book) with a goal to shift towards an 80%-20% order book split between Gujarat and other states.
- →Execution timelines for projects are typically 18 to 24 months, supporting steady revenue realization aligned with order inflows.
- →Growth is driven by increasing opportunities in transmission and distribution segments across multiple states including Maharashtra, Orissa, Jharkhand, Rajasthan, and Uttarakhand.
- →The company is also entering new segments like Battery Energy Storage Systems (BESS), adding potential new revenue streams.
📈 Profitability & Margins
- →Rajesh Power Services Ltd. targets a revenue CAGR of approximately 40% over the next 2-3 years, continuing their strong growth trajectory (Page 16, 13).
- →EBITDA margins are expected to stabilize around 11% to 12%, with PAT margins around 8% to 9%, maintaining healthy profitability (Pages 16, 36).
- →The company plans order inflows in the range of INR 4,000 to INR 5,000 crore yearly, supporting revenue growth (Page 16).
- →BESS (Battery Energy Storage Systems) segment is seen as a new growth engine, with the company aiming to expand its share in EPC projects there, though exact contribution to revenue is currently uncertain (Pages 13, 22).
- →Strong execution capabilities and operational efficiencies are expected to support these margins and growth rates.
- →Overall, sustained profitable growth and operational excellence are the focus areas according to the management’s strategy (Page 7).
🏗️ Capital Expenditure Plans
- →Rajesh Power Services is developing a 65 MW Battery Energy Storage System (BESS) project with GUVNL, expected to commission by September-October 2027.
- →The BESS project will be owned by the company, generating monthly rental income from the government (tariff rentals).
- →The company plans to invest equity in the BESS project, with 70%-80% project financing expected from banks and the rest through equity.
- →CapEx for BESS infrastructure is approximately INR 1.5 to 2.5 crore per MW.
- →The BESS project serves as a strategic entry to understand the BESS ecosystem, aiding in bidding for larger BESS EPC projects.
- →Rajesh Power is expanding capabilities beyond 220 kV transmission to 400 kV GIS substations, with this new capability positioning them for future 765 kV segment opportunities.
- →They are exploring automation, e.g., automated cable winch machines, to scale cable laying operations efficiently.
💰 Fundraising & Capital Structure
- →Management mentioned working with lenders for project financing, targeting around 70% to 80% debt financing from banks, with the remaining being equity from the company.
- →The exact project size and corresponding equity amount are still being determined, so no specific numbers were provided yet.
- →There was no explicit mention of new equity fundraising plans during the call.
- →The company appears focused on balancing debt and equity financing to fund ongoing and upcoming projects but has not announced any immediate new fundraising through debt or equity.
📋 Order Book & Pipeline
- →Current order book stands at approximately INR 3,326 crores as of H2FY26.
- →Around 85% to 90% of the current order book is linked to Gujarat, with plans to increase projects outside Gujarat to an 80-20 split.
- →Order inflow for FY26 was around INR 2,743 crores, including some L1 orders (~INR 210 crores).
- →Management is targeting an order book closing above INR 5,000 crores for FY27.
- →Bids worth INR 2,200 crores, awaited with results expected by May end to June early 2026.
- →Plans to aggressively bid outside Gujarat to diversify the order book.
- →The addressable market opportunity from key states (Gujarat, Rajasthan, Uttarakhand) is estimated at INR 14,000-15,000 crores annually.
Key Metrics
Continue your research
What Rajesh Power Services Ltd's management said in earlier quarters
Others in Other Utilities this season
- Va Tech Wabag (Q3 FY26)
Emphasis on disciplined bidding to maintain 13%-15% EBITDA margins supports sustainable growth. Key concall takeaways from Va Tech Wabag Ltd's Q3 FY26 earnings…
- Enviro Infra Engineers Ltd (Q3 FY26)
INR 1,900 crores (Page 23). Key concall takeaways from Enviro Infra Engineers Ltd's Q3 FY26 earnings call — and how it ranks against sector peers.
- Ion Exchange (India) Ltd (Q3 FY26)
Consumer Products division showing strong 30% year-on-year volume growth with continued investments in advertising to build medium to long-term revenue…
- Antony Waste han (Q3 FY26)
90 crores to Rs. Key concall takeaways from Antony Waste Handling Cell Ltd's Q3 FY26 earnings call — and how it ranks against sector peers.
Frequently Asked Questions
What were Rajesh Power Services Ltd Q3 FY26 results?
Rajesh Power Services Ltd. Rajesh Power Services Ltd.
What is Rajesh Power Services Ltd share price analysis?
Rajesh Power Services Ltd currently shows a neutral. The stock trades at a P/E of 10.9 with a market cap of ₹1,506 Cr. Investors should review the full earnings analysis for detailed insights.
Is Rajesh Power Services Ltd planning capital expenditure?
Rajesh Power Services is developing a 65 MW Battery Energy Storage System (BESS) project with GUVNL, expected to commission by September-October 2027.
Keep Rajesh Power Services Ltd on your radar — track it to get its next earnings analysis in your feed.