Guj Inds. Power Q1 FY27 Earnings Call Analysis
Revenue, margin, capex, fundraise and order book outlook from management commentary.
Management growth scorecard
Revenue
Category 2
Margin
Category 3
Fundraise
Yes
Order
N/A
Capex
Yes
2 of 4 growth signals are positive.
Full analysisRevenue guidance
Category 2- →Revenue growth expected from commissioning of additional solar capacities at Khavda: 600 MW project to generate ~INR 420 crores revenue in FY26-27; 500 MW project pending evacuation, expected to add similar revenues once operational.
- →Incremental top line growth estimated around INR 400-450 crores from Khavda solar projects in FY26-27.
- →Renewable Energy (RE) park operations anticipated to add INR 20-25 crores net revenue annually over 25 years.
- →Overall EBITDA expected to rise substantially to about INR 950-1,000 crores by FY27 with full operation of 600 MW and 500 MW projects.
- →Additional solar capacity expansion planned, targeting 200-300 MW more over next few years, subject to land availability.
- →Thermal capacity expansion of 750 MW underway with phased capex; corresponding revenue growth expected post-2027.
- →Long-term capacity addition contingent on land and connectivity, with firm land allocation for 2,375 MW solar capacity at Khavda.
Margin guidance
Category 3- →FY27 EBITDA expected to reach INR950-1,000 crores, up from around INR600 crores in FY26 solar division alone.
- →EBITDA growth driven by full commissioning of 600 MW Khavda project and 500 MW upcoming capacity.
- →Revenue addition from 600 MW Khavda and renewable park expected around INR450 crores over FY26 base.
- →PBT is expected to be good post commissioning 500 MW, though initial teething losses may occur.
- →ROE (Return on Equity) excluding gas-based stations anticipated to exceed 13%-14%.
- →Peak debt expected around INR4,500 crores, with phased capex for thermal expansion (750 MW) from 2027-2033.
- →Thermal capacity expansion capex estimated at INR6,000 crores, with lignite supply fully secured.
- →Management committed to stable dividend policy aligned with profitability and cash flows.
3 more insights locked — sign up free to unlock
Fundraise plans
Yes- →No immediate plans to raise equity for the additional INR6,000 crores thermal capacity, but if required, equity may be raised through internal accruals, promoter infusion, or market dilution.
- →Projected financing for the 750 MW thermal expansion is expected as 80% debt (around INR4,800 crores) and 20% equity (around INR1,200 crores).
- →Peak debt anticipated around INR4,500 crores after commissioning the 500 MW project, with phased debt addition and repayments over time.
- →For the proposed 200 MW solar capacity addition at Khavda, estimated project cost is INR800-1,000 crores involving a small incremental debt of about INR200-300 crores, minimal impact on the overall debt.
- →Current debt repayments structured with moratorium ending June 2026; repayment expected without significant issues given cash flows from operational assets.
Order book
- →Pending orders primarily relate to the 750 MW thermal lignite-based power station expansion.
- →Approval has been given by GUVNL in principle under Section 62 cost-plus basis for this expansion.
- →Tender for the project has been floated and is currently under observation by BHEL and other parties.
- →The order is expected to be placed by the end of the current financial year or last quarter.
- →Post-order placement, the project will commence, with a target to commission 3 units of 250 MW each over the next three to four years.
- →For the 500 MW project, borrowing and capitalization processes are ongoing; the commissioning is in advanced stages, awaiting power evacuation readiness.
- →Battery Energy Storage System (BESS) tenders are in place for Baroda location to repurpose gas-based plant facilities.
- →No explicit mention of a formal orderbook figure, but multiple tenders and projects are active with timelines extending over next 1-4 years.
Capex plans
Yes- →**500 MW Solar Project at Khavda:** Capital work in progress ~INR2,065 crores; expected commissioning post-monsoon 2026; associated peak debt around INR4,500 crores after full commissioning.
- →**Additional 200-300 MW Solar Capacity:** Planned medium-term addition subject to land availability; part of the pipeline beyond 1,100 MW capacity.
- →**Battery Energy Storage System (BESS):** Conversion of Baroda gas plant site into BESS; first phase 20/120 MW approved with INR250-300 crores capex; potential future expansions planned.
- →**750 MW Thermal Lignite-based Expansion:** Capex INR6,000-7,000 crores phased over 2027-2032/33; includes three 250 MW units; approved by GUVNL and tender process underway.
- →**Pumped Storage Projects:** Location identification ongoing; bids being prepared to secure government projects.
- →**Solar Park Development Revenues:** Acting as park developer for Khavda park (2,375 MW total), expected to generate INR20-25 crores net revenue annually via O&M services for 25 years.
How does Guj Inds. Power rank vs peers in Power?
Pro featureSee full Power sector rankings
How does Guj Inds. Power rank in Power?
Compare Guj Inds. Power against every Power company (Q1 FY27) on revenue, margins and earnings-call signals.