ACME Solar Holdings commissions Phase-III of Battery Energy Storage System in Rajasthan

ACME Solar Holdings Ltd · Power

What the filing says

  • ACME Greentech Seventh Private Limited commissioned 53.63 MW/214.52 MWh of BESS on Sept 30, 2026
  • Phase-III is part of a 300 MW / 1200 MWh FDRE project at Kelan village, Bikaner, Rajasthan
  • Total commissioned BESS capacity now 159.58 MW / 638.32 MWh; PPA signed with SJVN Limited

Original filing

Update On Commissioning Of Battery Energy Storage System (BESS) Project

Read the filing on BSE (PDF) →

Companies guiding to strong growth

Ranked by management's own guidance on revenue and margins — not by us.

Waaree Energies

Electrical Equipment

Revenue: Rank 1Margin: Rank 1

Sign up free to see all 6 →

See full rankings

Rank buckets describe management commentary on revenue and margin. Not investment advice, and not a forecast of returns.

More from ACME Solar Holdings Ltd

Other capex / expansion filings this fortnight

All capex / expansion filings →

Summary written by Arthneeti from the company's filing with the stock exchange; check the original filing for full details. Arthneeti is a research and analytics platform, not a SEBI-registered investment adviser, and nothing here is a recommendation to buy or sell.