Capex / expansionNotableFiled on BSE ·

ACME Solar commissions 66.68 MW solar component of Hybrid Power Project

ACME Solar Holdings · Power

Arthneeti Research DeskPublished 1 min read

Key highlights

  • ACME Renewtech Pvt Ltd commissioned additional 66.68 MW solar at Kelan, Bikaner on Nov 2, 2026
  • Commercial Operation Date for this capacity is Nov 4, 2026
  • Total commissioned solar capacity in the Hybrid Project is now 200.04 MW out of 300 MW; PPA signed with NTPC Limited

Why it's rated notable: The filing states a further 66.68 MW commissioned on a 300 MW project with 200.04 MW now cumulative and a signed PPA with NTPC Limited, but gives no rupee value, so the level stays at medium.

Original filing

Update On Commissioning Of Solar Component Of The Hybrid Power Project

Read the filing on BSE (PDF) →

Companies guiding to strong growth

Ranked by management's own guidance on revenue and margins — not by us.

Waaree Energies Ltd

Electrical Equipment

Revenue growth 40%+Margin up 2%+

Sign up free to see all 6 →

See full rankings

Rank buckets describe management commentary on revenue and margin. Not investment advice, and not a forecast of returns.

More from ACME Solar Holdings

Other capex / expansion filings this fortnight

All capex / expansion filings →

Summary written by Arthneeti from the company's filing with the stock exchange; check the original filing for full details. Arthneeti is a research and analytics platform, not a SEBI-registered investment adviser, and nothing here is a recommendation to buy or sell.