Order winFiled on BSE ·

GHV Infra Projects Ltd concludes EPC contract for Erisha Smart Manufacturing Hub

GHV Infra Projects Ltd · Construction

What the filing says

  • EPC contract with Rana Exim FZ-LLC and GHV Infra FZ-LLC concluded in 2nd week of September 2026
  • Project delayed due to pending Master Plan approval by Employer and ongoing War in West Asia since February 2026
  • GHV suspended works from mid-August 2026 citing Employer's failure on financial arrangements and risk of payments

Original filing

Disclosure Under Regulation 30 Of SEBI (LODR) 2015 - Conclusion Of Contract

Read the filing on BSE (PDF) →

Companies guiding to strong growth

Ranked by management's own guidance on revenue and margins — not by us.

Waaree Energies

Electrical Equipment

Revenue: Rank 1Margin: Rank 1

Sign up free to see all 6 →

See full rankings

Rank buckets describe management commentary on revenue and margin. Not investment advice, and not a forecast of returns.

Other order win filings this fortnight

All order win filings →

Summary written by Arthneeti from the company's filing with the stock exchange; check the original filing for full details. Arthneeti is a research and analytics platform, not a SEBI-registered investment adviser, and nothing here is a recommendation to buy or sell.