Godawari Power & Ispat Ltd Q2 FY26 key numbers

Revenue
New pellet plant (2 million ton expansion) to start commercial production soon, with ramp-up expected within 4 to 6 weeks.

As stated in Godawari Power & Ispat Ltd's Q2 FY26 earnings call transcript · published 18 Jul 2026. Reported figures, not investment advice.

The short version

Pellet production is expected to reach a bare minimum of 4 million tons in FY '27, with potential to be higher; 80% capacity utilization expected from Q4 of the current year. GPIL expects to meet its FY '26 production targets despite a pellet plant incident, indicating stable operational performance.

From Godawari Power & Ispat Ltd's Q2 FY26 earnings-call transcript · updated 16 Oct 2026.

Revenue & Sales Performance

  • Pellet production is expected to reach a bare minimum of 4 million tons in FY '27, with potential to be higher; 80% capacity utilization expected from Q4 of the current year.
  • Expanded iron ore mining at Ari Dongri targets 4.7 to 5 million tons in FY '27, with additional beneficiation capacity increasing from 0.6 million to 6 million tons by Q2 FY '27.
  • New pellet plant (2 million ton expansion) to start commercial production soon, with ramp-up expected within 4 to 6 weeks.
  • Sponge iron production is stable at 0.5 million tons, with plans to eliminate sponge sales by next year through new furnace addition.

2 more points from Godawari Power & Ispat Ltd's call on revenue

Create a free account to keep reading this call

Profitability & Margins

See what Godawari Power & Ispat Ltd said on profitability & margins — free account, 30 seconds.

Capital Expenditure Plans

  • Additional 250 MW solar power capacity approved, expected commissioning by Q4 FY '27 for CRM project and integrated steel plant; cost-effective with ~24% IRR.
  • 0.7 million ton Cold Rolling Mill (CRM) complex underway; land acquired, major equipment orders placed; total cost INR 900 crores (INR 600 crores debt-funded).
  • 1 million ton integrated steel plant planned post iron ore capacity expansion; Board approval pending final mining EC.
  • Battery Energy Storage System (BESS) project of 10 GW in Maharashtra by Godawari New Energy Pvt Ltd; land (112 acres) acquired; INR 700 crores cost, 60% debt-funded.

2 more points from Godawari Power & Ispat Ltd's call on capex

Create a free account to keep reading this call

Top-ranked in Industrial Products

Ranked on what management guided this quarter

Guidance-ranked
Rev 1Mar 1
2Shera Energy
Rev 1Mar 1
3
Rev 1Mar 1
4
Rev 1Mar 2
5
Rev 1Mar 2
Sign up free to see 3 moreTakes 30 seconds · no cardSign up

Rank buckets describe management commentary on revenue and margin. Not investment advice, and not a forecast of returns.

Fundraising & Capital Structure

See what Godawari Power & Ispat Ltd said on fundraising & capital structure — free account, 30 seconds.

Order Book & Pipeline

  • The management discussed order placements for the CRM (Cold Rolled Mill) project have been completed in the second quarter.
  • Battery Energy Storage System (BESS) project is in progress with land acquired, and infrastructure work expected to start next month.
  • Machine orders for both CRM and BESS projects have begun being placed with suppliers in India and China.

2 more points from Godawari Power & Ispat Ltd's call on order book

Create a free account to keep reading this call

Godawari Power & Ispat Ltd — Quarterly revenue & net profit

Revenue Net profit
Dec 2024Q3 FY25
Mar 2025Q4 FY25
Jun 2025Q1 FY26
Sep 2025Q2 FY26
Dec 2025Q3 FY26
Mar 2026Q4 FY26

Reported quarterly figures (₹ Cr). Latest (Q4 FY26): revenue ₹1.6K Cr, net profit ₹280 Cr. Revenue and profit are scaled separately — hover a quarter for exact figures.

Full financials →

Others in Industrial Products this season

  • Lead Reclaim and Rubber Products Ltd (Q2 FY26)

    Revenue from Operations for H1 FY26: ₹2,190 lakhs, up 138.04% YoY (from ₹920 lakhs in H1 FY25) (Page 19) . Key investor presentation takeaways from Lead Reclaim

  • Shubhshree Biofuels Energy Ltd (Q2 FY26)

    Revenue from operations for H1 FY26: ₹9,604.6 Lakhs . Key investor presentation takeaways from Shubhshree Biofuels Energy Ltd's Q2 FY26 investor presentation —

  • De Neers Tools Ltd (Q2 FY26)

    H1FY26 Net Sales:** ₹670.4 Mn . Key investor presentation takeaways from De Neers Tools's Q2 FY26 investor presentation — and how it ranks against sector peers.

  • WOL 3D India Ltd (Q2 FY26)

    Revenue from Operations for H1FY26 is Rs 415 Mn, up 82% YoY from Rs 227 Mn in H1FY25 (Page 9, Page 5). Key investor presentation takeaways from WOL 3D India Ltd

🔎 Who's planning the most growth?

Companies ranked by management's own guidance — revenue, margins, capex and order book, from every earnings call in India.

See rankings →

Arthneeti Pro · Annual

Godawari Power & Ispat Ltd and 15K+ more earnings calls,
for less than your morning chai

a day

Every earnings call, ranking and concall Q&A across all four results seasons.

Secure Razorpay payment · instant access

Frequently Asked Questions

What were Godawari Power & Ispat Ltd Q2 FY26 results?

Pellet production is expected to reach a bare minimum of 4 million tons in FY '27, with potential to be higher; 80% capacity utilization expected from Q4 of the current year. GPIL expects to meet its FY '26 production targets despite a pellet plant incident, indicating stable operational performance.

What is Godawari Power & Ispat Ltd share price analysis?

Godawari Power & Ispat Ltd currently shows a neutral. The stock trades at a P/E of 17.4 with a market cap of ₹14,253 Cr. Investors should review the full earnings analysis for detailed insights.

Is Godawari Power & Ispat Ltd planning capital expenditure?

Additional 250 MW solar power capacity approved, expected commissioning by Q4 FY '27 for CRM project and integrated steel plant; cost-effective with ~24% IRR.