Borosil Renewables Ltd updates on furnace capacity expansion project and cost revision

Borosil Renew. · Industrial Products

What the filing says

  • 600 TPD via two 300 TPD furnaces (SG-4 & SG-5) now expected by end March 2027, originally scheduled for December 2026
  • Revised project cost estimate approx. Rs. 1100 crores for 600 TPD, versus original Rs. 950 crores
  • Additional cost outlay of Rs. 150 crores for scope expansion to be entirely met through internal funds without increase in borrowings

Why it's rated major development: The Board approved a revised cost of approx. Rs. 1100 crores and March 2027 commissioning for 600 TPD, a 60% addition to the existing 1000 TPD, against an original Rs. 950 crores and December 2026 timeline.

Figures checked against the filing by a second AI read, which corrected the first summary. About the business, not the share price.

Original filing

Board Meeting Outcome for Outcome Of Board Meeting - Update On Capacity Expansion

Read the filing on BSE (PDF) →

Companies guiding to strong growth

Ranked by management's own guidance on revenue and margins — not by us.

Waaree Energies Ltd

Electrical Equipment

Revenue growth 40%+Margin up 2%+

Sign up free to see all 6 →

See full rankings

Rank buckets describe management commentary on revenue and margin. Not investment advice, and not a forecast of returns.

Other capex / expansion filings this fortnight

All capex / expansion filings →

Summary written by Arthneeti from the company's filing with the stock exchange; check the original filing for full details. Arthneeti is a research and analytics platform, not a SEBI-registered investment adviser, and nothing here is a recommendation to buy or sell.