Capex / expansionFiled on BSE ·

Juniper Green Energy commissions 40 MW wind capacity in hybrid project

Juniper Green · Power

What the filing says

  • Juniper Green Spark Four Pvt Ltd, subsidiary of Juniper Green Energy Ltd, commissioned 40 MW wind capacity in 120 MW Wind Solar Hybrid Project on September 11, 2026.
  • Commissioning witnessed by Gujarat Energy Development Agency and Paschim Gujarat Vij Company Ltd; formal certificate pending.
  • Total operational capacity of Juniper Green Energy Ltd and subsidiaries now approx. 2,679 MWp and 500 MWh BESS.

Original filing

Intimation Under Regulation 30 (LODR) - Update On Commissioning Of Additional Capacity

Read the filing on BSE (PDF) →

Companies guiding to strong growth

Ranked by management's own guidance on revenue and margins — not by us.

Waaree Energies

Electrical Equipment

Revenue: Rank 1Margin: Rank 1

Sign up free to see all 6 →

See full rankings

Rank buckets describe management commentary on revenue and margin. Not investment advice, and not a forecast of returns.

More from Juniper Green

Other capex / expansion filings this fortnight

All capex / expansion filings →

Summary written by Arthneeti from the company's filing with the stock exchange; check the original filing for full details. Arthneeti is a research and analytics platform, not a SEBI-registered investment adviser, and nothing here is a recommendation to buy or sell.