Studds Accessories updates delay and new expected start for Manufacturing Facility-V
Studds Accessor. · Auto Components
What the filing says
- Commercial production at Manufacturing Facility-V, Faridabad, delayed beyond Q2 FY 2027.
- Occupation Certificate for facility received on September 30, 2026.
- Commercial production now expected by end of October 2026, pending final approvals.
Original filing
Update On Commercial Production At Manufacturing Facility-V
Read the filing on BSE (PDF) →Companies guiding to strong growth
Ranked by management's own guidance on revenue and margins — not by us.
Waaree Energies
Electrical Equipment
Revenue growth 40%+Margin up 2%+
Sign up free to see all 6 →
See full rankingsRank buckets describe management commentary on revenue and margin. Not investment advice, and not a forecast of returns.
Other capex / expansion filings this fortnight
- Capex / expansionBondada Engineering LtdBondada Engineering commissions 221.7 MWp solar projects in Q2 FY27
- Capex / expansionLords Mark IndustriesLord's Mark Industries' promoter sells shares and proposes reinvestment for expansion
- Capex / expansionJayaswal Neco Industries LtdJayaswal Neco Industries achieves financial closure for 1.5 MnTPA pellet plant expansion
- Capex / expansionACME Solar Holdings LtdACME Solar commissions additional 107.36 MW / 437.49 MWh BESS capacity in Rajasthan
- Capex / expansionLloyds MetalsLloyds Metals & Energy reports record H1FY27 production across key segments
- Capex / expansionAdani Green Energy LtdAdani Green Energy operationalizes 481.9 MW renewable and 6.63 GWh BESS projects
Summary written by Arthneeti from the company's filing with the stock exchange; check the original filing for full details. Arthneeti is a research and analytics platform, not a SEBI-registered investment adviser, and nothing here is a recommendation to buy or sell.