The short version
Revenue for Q3 25-26: ₹316.79 crores (Page 7) - Revenue for Q3 24-25: ₹351.59 crores (Page 7) - Year-on-year change: Approximately -9.9% (decline from ₹351.59 to ₹316.79 crores) - Tu Quarterly EBITDA: ₹7.15 crore (Q3 25-26) down 72% from ₹25.93 crore in Q2 25-26 - EBITDA Margin: 1.90% in Q3 25-26, down from 8.19% in Q2 25-26 (decline of 6.29%) - Operating Cost: ₹349.
From RPP Infra Projects Ltd's Q3 FY26 earnings-call transcript · updated 16 Oct 2026.
Revenue & Sales Performance
- Revenue for Q3 25-26: ₹316.79 crores (Page 7)
- Revenue for Q3 24-25: ₹351.59 crores (Page 7)
- Year-on-year change: Approximately -9.9% (decline from ₹351.59 to ₹316.79 crores)
- Turnover trend: Graph on Page 9 shows turnover decreasing from around 351.59 Cr (Q3 24-25) to 316.76 Cr (Q3 25-26)
- Volume outlook:
- Around ₹1,600 crores worth of projects expected to start generating revenue by end of Q4 25-26 and continuing into Q1 FY 26-27 (Page 8)
- Expect revenue contribution and profit improvement from Q1 of next financial year (Page 8)
- Additional details:
2 more points from RPP Infra Projects Ltd's call on revenue
Pro opens every point from 15K+ earnings calls
Profitability & Margins
See what RPP Infra Projects Ltd said on profitability & margins — free account, 30 seconds.
Capital Expenditure Plans
- RPP Infra awarded ₹1126.50 crores project, led by MD Mr. P. Arul Sundaram.
- Received 15 acres land from BHEL in Varanasi, UP for factory establishment.
- Factory to produce 1,20,000 tons of fabricated structures over 5 years.
- Estimated factory establishment cost (civil work, machinery) ₹62 Crores.
- Factory expected completion by end April 2026 or early May 2026.
- Production start target: monthly 2200 to 2500 tons fabricated structures.
- Working capital facility of ₹85 Crores sanctioned by IDFC First Bank for this project (approval pending).
2 more points from RPP Infra Projects Ltd's call on capex
Pro opens every point from 15K+ earnings calls
Fundraising & Capital Structure
See what RPP Infra Projects Ltd said on fundraising & capital structure — free account, 30 seconds.
Order Book & Pipeline
- Current order book as of December 2025 consists of 41 projects with ₹3,963.66 crores worth of work remaining to be executed.
- The company is in L1 stage for two more tenders valued at ₹260 crores.
- During the current year up to December 2025, 10 new projects worth ₹2,336.78 crores were awarded.
- Breakdown of the 10 new projects awarded: Infrastructure – ₹1,962.91 crores (8 projects), Buildings – ₹8.03 crores (1 project), Water management – ₹365.85 crores (1 project).
2 more points from RPP Infra Projects Ltd's call on order book
Pro opens every point from 15K+ earnings calls
RPP Infra Projects Ltd — Quarterly revenue & net profit
Reported quarterly figures (₹ Cr). Latest: revenue ₹380 Cr, net profit ₹1 Cr. Revenue and profit are scaled separately — hover a quarter for exact figures.
Full financials →Continue your research
What RPP Infra Proj.'s management said in earlier quarters
Others in Construction this season
- Likhitha Infra. (Q3 FY26)
Year-on-Year change in revenue: Decrease of approximately 39.59% . Key investor presentation takeaways from Likhitha Infrastructure Ltd's Q3 FY26 investor prese
- SEPC (Q3 FY26)
Q3 FY26 Revenue:** ₹340.97 Cr . Key investor presentation takeaways from SEPC Ltd's Q3 FY26 investor presentation — and how it ranks against sector peers.
- GK Energy (Q3 FY26)
Q3 FY26 Revenue from Operations (Standalone): ₹460.20 Crores, up 43.64% YoY from ₹320.38 Crores in Q3 FY25 (Page 21). Key investor presentation takeaways from G
- MBL Infrast (Q3 FY26)
MBL is pre-qualified for the ‘User Fee Collection’ tender of NHAI with a net worth of ₹1,244 crores (FY24). Key investor presentation takeaways from MBL Infrast
Arthneeti Pro · Annual
RPP Infra Projects Ltd and 15K+ more earnings calls,
for less than your morning chai
a day
Every earnings call, ranking and concall Q&A across all four results seasons.
Secure Razorpay payment · instant access
Frequently Asked Questions
What were RPP Infra Projects Ltd Q3 FY26 results?
Revenue for Q3 25-26: ₹316.79 crores (Page 7) - Revenue for Q3 24-25: ₹351.59 crores (Page 7) - Year-on-year change: Approximately -9.9% (decline from ₹351.59 to ₹316.79 crores) - Tu Quarterly EBITDA: ₹7.15 crore (Q3 25-26) down 72% from ₹25.93 crore in Q2 25-26 - EBITDA Margin: 1.90% in Q3 25-26, down from 8.19% in Q2 25-26 (decline of 6.29%) - Operating Cost: ₹349.
What is RPP Infra Projects Ltd share price analysis?
RPP Infra Projects Ltd currently shows a neutral. The stock trades at a P/E of 123.9 with a market cap of ₹256 Cr. Investors should review the full earnings analysis for detailed insights.
Is RPP Infra Projects Ltd planning capital expenditure?
RPP Infra awarded ₹1126.50 crores project, led by MD Mr.
Keep RPP Infra Projects Ltd on your radar — track it to get its next earnings analysis in your feed.
This analysis is AI-generated based on publicly available earnings data and the company's investor presentation. This is not investment advice. Please consult a SEBI-registered advisor before making investment decisions.