Sarda Energy Q1 FY27 earnings call: Revenue & Margins

Q1 FY27 earnings call: what management guided on revenue, margins and order book.

Price₹506
Market cap₹18.0K Cr
P/E16.0
Updated25 Aug 2026
Read4 min read

The short version

Mineral wool project sales expected to ramp up to full capacity within 3-6 months, targeting INR 90-110 crores revenue in FY27 (page 13). FY27 revenue from mineral wool project expected around INR 90-110 crores with capacity ramp-up in next 6 months.

From Sarda Energy's Q1 FY27 earnings-call transcript · updated 25 Aug 2026.

Revenue & Sales Performance

  • Mineral wool project sales expected to ramp up to full capacity within 3-6 months, targeting INR 90-110 crores revenue in FY27 (page 13).
  • Ramp-up in mineral wool production anticipated in next two quarters, currently at ~60-65% capacity (page 13).
  • Steel and ferro alloy prices expected to remain stable; ferro alloys margins may improve due to softer raw material prices (page 12).
  • Power generation expected to increase with commissioning of 30 MW captive power plant, and better power prices in Q2 FY27 (page 10).
  • IPP power generation anticipated to surpass last year's 415 crore units with better PLFs and commissioned expansions (page 10).
  • Expansion projects like 66 MW Arunachal hydro and 50 MW solar proceeding; commissioning targeted in FY27 and next quarters respectively (pages 11-12).

2 more points from Sarda Energy's call on revenue

Pro opens every point from 15K+ earnings calls

Profitability & Margins

See what Sarda Energy said on profitability & margins — free account, 30 seconds.

Capital Expenditure Plans

  • Investing approx. INR 300 crores in a waste heat recovery power plant at Vizag to improve energy efficiency and resource utilization.
  • Ongoing expansions funded through internal accruals; company is net debt-free with healthy liquidity of over INR 2,500 crores as of June 2026.
  • Expanding thermal power capacity at SKS from 600 MW to 1,200 MW; regulatory approvals in progress.
  • Commissioning of 50 MW captive solar project delayed due to right-of-way issues; expected commissioning before end of next quarter.
  • Development of Shahpur West high-grade coal mine on schedule; commissioning targeted before end of FY27.
  • Bartunga Hill coal mine expected to open by end of next financial year.

2 more points from Sarda Energy's call on capex

Pro opens every point from 15K+ earnings calls

Top-ranked in Ferrous Metals

Ranked on what management guided this quarter

Guidance-ranked
Rev 2Mar 3
3
Rev 2Mar 3
4
Rev 3Mar 1
5
Rev 3Mar 2
Sign up free to see 3 moreTakes 30 seconds · no cardSign up

Rank buckets describe management commentary on revenue and margin. Not investment advice, and not a forecast of returns.

Fundraising & Capital Structure

See what Sarda Energy said on fundraising & capital structure — free account, 30 seconds.

Order Book & Pipeline

The transcript does not explicitly mention the current or expected order book or pending orders for Sarda Energy & Minerals Limited. However, relevant project and demand highlights include: - Strong demand in mineral wool project, with sales lagging due to production ramp-up delays. - Large demand for steel and ferroalloys; production affected by planned outages but expected to improve. - Over 380 MW of medium and long-term power purchase agreements (PPAs) secured out of 710 MW saleable capacity, improving revenue visibility. - Ongoing capacity expansions: thermal power capacity at SKS doubling to 1,200 MW, small hydro projects (74 MW), 50 MW captive solar project.

2 more points from Sarda Energy's call on order book

Pro opens every point from 15K+ earnings calls

Sarda Energy — Quarterly revenue & net profit

Revenue Net profit
Dec 2024Q3 FY25
Mar 2025Q4 FY25
Jun 2025Q1 FY26
Sep 2025Q2 FY26
Dec 2025Q3 FY26
Mar 2026Q4 FY26

Q1 FY27 figures are not in this chart yet. Latest shown: Mar 2026 (Q4 FY26). The Q1 FY27 numbers from the filing are in the analysis on this page.

Reported quarterly figures (₹ Cr). Latest (Q4 FY26): revenue ₹1.3K Cr, net profit ₹155 Cr. Revenue and profit are scaled separately — hover a quarter for exact figures.

Full financials →

Others in Ferrous Metals this season

  • Vedanta Iron & Steel (Q1 FY27)

    ₹3,612 crore in Q1 FY27, up 18% YoY (Page 3, 26, 29) . Key concall takeaways from Vedanta Iron & Steel Ltd's Q1 FY27 earnings call — and how it ranks against…

  • Sandur Manganese (Q1 FY27)

    Q1FY27 Standalone Revenue: ₹554 crore (27% YoY growth) . Key concall takeaways from Sandur Manganese & Iron Ores Ltd's Q1 FY27 earnings call — and how it ranks…

  • Tata Steel Ltd (Q1 FY27)

    Return on invested capital in India is strong at ~27%, indicating healthy profitability prospects. Key concall takeaways from Tata Steel Ltd's Q1 FY27 earnings…

  • JSW Steel Ltd (Q1 FY27)

    22,000-24,000 crores planned for FY27 to support growth and expansions. Key concall takeaways from JSW Steel's Q1 FY27 earnings call — and how it ranks against…

🔎 Who's planning the most growth?

Companies ranked by management's own guidance — revenue, margins, capex and order book, from every earnings call in India.

See rankings →

Arthneeti Pro · Annual

Sarda Energy and 15K+ more earnings calls,
for less than your morning chai

a day

Every earnings call, ranking and concall Q&A across all four results seasons.

Secure Razorpay payment · instant access

Frequently Asked Questions

What were Sarda Energy Q1 FY27 results?

Mineral wool project sales expected to ramp up to full capacity within 3-6 months, targeting INR 90-110 crores revenue in FY27 (page 13). FY27 revenue from mineral wool project expected around INR 90-110 crores with capacity ramp-up in next 6 months.

What is Sarda Energy share price analysis?

Sarda Energy currently shows a neutral. The stock trades at a P/E of 16.0 with a market cap of ₹17,993 Cr. Investors should review the full earnings analysis for detailed insights.

Is Sarda Energy planning capital expenditure?

Investing approx.

Keep Sarda Energy on your radar — track it to get its next earnings analysis in your feed.

This analysis is AI-generated based on publicly available earnings data and the company's earnings call transcript. This is not investment advice. Please consult a SEBI-registered advisor before making investment decisions.