Capex / expansionFiled on BSE ·
ACME Solar Holdings commissions additional 66.68 MW solar capacity in Rajasthan
ACME Solar Hold. · Power
What the filing says
- ACME Renewtech Private Limited, subsidiary of ACME Solar Holdings, commissioned 66.68 MW solar capacity at Village Kelan, Tehsil-Chhatargarh, District-Bikaner, Rajasthan on October 5, 2026
- Commercial Operation Date (COD) for this capacity is October 7, 2026
- Total commissioned solar capacity of ACME Renewtech under the 300 MW Hybrid Power Project is now 133.36 MW, with PPA signed with NTPC Limited
Original filing
Update On Commissioning Of Solar Component Of The Hybrid Power Project
Read the filing on BSE (PDF) →Companies guiding to strong growth
Ranked by management's own guidance on revenue and margins — not by us.
Waaree Energies
Electrical Equipment
Revenue growth 40%+Margin up 2%+
Sign up free to see all 6 →
See full rankingsRank buckets describe management commentary on revenue and margin. Not investment advice, and not a forecast of returns.
More from ACME Solar Hold.
- Capex / expansionACME Solar commissions Phase-I of Battery Energy Storage System in Rajasthan
- Capex / expansionACME Solar Holdings commissions Phase-III of Battery Energy Storage System in Rajasthan
- Capex / expansionACME Solar commissions additional 107.36 MW / 437.49 MWh BESS capacity in Rajasthan
- Capex / expansionACME Solar Holdings commissions 52.32 MW/209.28 MWh Phase-II BESS in Rajasthan
- Capex / expansionACME Solar commissions 66.68 MW solar and 300 MWh BESS capacity in Rajasthan
Other capex / expansion filings this fortnight
- Capex / expansionBMW IndustriesBMW Industries Limited commissions Colour Coating Line at Bokaro complex
- Capex / expansionJSW Energy LtdJSW Energy’s Installed Capacity Reaches 15.1 GW with 1.7 GW Added Since April 2026
- Capex / expansionUltraTech Cement LtdUltraTech Cement surpasses 2 GW green energy capacity for captive use in India
- Capex / expansionVedanta LtdVedanta Limited announces production results for Q2 and H1 FY27 ending Sept 30, 2026
- Capex / expansionVedanta Aluminium Metal LtdVedanta Aluminium Metal Limited reports Q2 FY27 production results ending Sept 30, 2026
- Capex / expansionStudds Accessor.Studds Accessories updates delay and new expected start for Manufacturing Facility-V
Summary written by Arthneeti from the company's filing with the stock exchange; check the original filing for full details. Arthneeti is a research and analytics platform, not a SEBI-registered investment adviser, and nothing here is a recommendation to buy or sell.