  • Project to evacuate power from 3X800 MW Pirpainti STPP in Bihar, commissioned by Q4 2028
  • Adds 881 ckm transmission lines and 3,160 MVA transformation capacity, annual tariff ~₹500 crore
  • To be executed via SPV Vikramshila Power Transmission Ltd under TBCB mechanism

Original filing

Announcement under Regulation 30 (LODR)-Press Release / Media Release

Read the filing on BSE (PDF) →

Companies guiding to strong growth

Ranked by management's own guidance on revenue and margins — not by us.

Knowledge Marine

Engineering Services

Revenue growth 40%+Margin up 2%+

Sign up free to see all 6 →

See full rankings

Rank buckets describe management commentary on revenue and margin. Not investment advice, and not a forecast of returns.

More from Adani Energy Solutions

Other capex / expansion filings this fortnight

All capex / expansion filings →

Summary written by Arthneeti from the company's filing with the stock exchange; check the original filing for full details. Arthneeti is a research and analytics platform, not a SEBI-registered investment adviser, and nothing here is a recommendation to buy or sell.