JSW Energy commissions 1,081 MW renewable capacity, total capacity now 14,535 MW

JSW Energy · Power

Arthneeti Research DeskPublished 1 min read
61%Capex / expansion

Key highlights

  • Commissioned 1,081 MW renewable energy since April 2026: 442 MW solar, 108 MW wind, 381 MW hybrid, 150 MW hydro
  • Total installed capacity reached 14,535 MW with 61% from renewables, 5,658 MW thermal capacity
  • Wind blade manufacturing facility at Halol, Gujarat, commissioned in June 2026 with annual capacity to support 600 MW wind installations

Why it's rated notable: The filing reports completed commissioning of 1,081 MW of renewable capacity with no rupee amount stated, so the level stays at medium.

Original filing

Capacity Addition

Read the filing on BSE (PDF) →

Companies guiding to strong growth

Ranked by management's own guidance on revenue and margins — not by us.

Rossell Techsys

Aerospace & Defense

Revenue growth 40%+Margin up 2%+

Sign up free to see all 6 →

See full rankings

Rank buckets describe management commentary on revenue and margin. Not investment advice, and not a forecast of returns.

More from JSW Energy

Other capex / expansion filings this fortnight

All capex / expansion filings →

Summary written by Arthneeti from the company's filing with the stock exchange; check the original filing for full details. Arthneeti is a research and analytics platform, not a SEBI-registered investment adviser, and nothing here is a recommendation to buy or sell.