Megatherm Induction Limited announces transformer division expansion project

Megatherm Induction · Industrial Products

Arthneeti Research DeskPublished 1 min read
₹70.1 CrCapex / expansion

Key highlights

  • Total project cost is ₹70.05 crore, with ₹39.75 crore in Phase 1 and ₹30.30 crore in Phase 2
  • New Shed 2 at Kharagpur to produce larger transformers including inverter-duty, furnace-duty, cast resin dry-type, and 220 kV units
  • Expansion supports demand from solar, storage, steel, data centres, and industrial markets with phased build and in-house production of smaller units

Original filing

General Updates

Read the filing on NSE (PDF) →

Companies guiding to strong growth

Ranked by management's own guidance on revenue and margins — not by us.

Knowledge Marine

Engineering Services

Revenue growth 40%+Margin up 2%+

Sign up free to see all 6 →

See full rankings

Rank buckets describe management commentary on revenue and margin. Not investment advice, and not a forecast of returns.

Other capex / expansion filings this fortnight

All capex / expansion filings →

Summary written by Arthneeti from the company's filing with the stock exchange; check the original filing for full details. Arthneeti is a research and analytics platform, not a SEBI-registered investment adviser, and nothing here is a recommendation to buy or sell.