For FY 2026, revenue is expected to be around 8% to 10% lower than FY 2025 due to delayed project starts and slow execution. For FY'26, revenue is expected to be approximately 8-10% lower than the previous year due to delayed project starts, with PAT showing growth due to exceptional items.
From Ashoka Buildcon Ltd's Q3 FY26 earnings-call transcript · updated 23 Aug 2026.
Revenue & Sales Performance
- For FY 2026, revenue is expected to be around 8% to 10% lower than FY 2025 due to delayed project starts and slow execution.
- FY 2027 is projected to witness approximately 15% growth in revenue over FY 2026, driven by new project acquisitions and improved order book execution.
- The order book intake expectation for FY 2026 is around INR 3,000-3,500 crore in the next two months.
- For FY 2027, the company targets an order book intake of approximately INR 11,000 to INR 12,000 crore.
2 more points from Ashoka Buildcon Ltd's call on revenue
Pro opens every point from 15K+ earnings calls
Profitability & Margins
See what Ashoka Buildcon Ltd said on profitability & margins — free account, 30 seconds.
Capital Expenditure Plans
- Q3 FY26 capex was approximately INR 15 crores.
- Expected capex in Q4 FY26 is around INR 25 crores.
- Total capex for the year FY26 expected to be around INR 75-80 crores.
- HAM equity investment balance is approximately INR 320 crores.
- Out of this, INR 220 crores is for the new HAM project Bowaichandi, and the balance is for Tumkur-Shivamogga III and IV.
- Further INR 180 crores planned to be invested by March 2026-27, split approximately INR 72 crores for March '26-'27 and INR 72 crores for March '27-'28, depending on appointed date.
2 more points from Ashoka Buildcon Ltd's call on capex
Pro opens every point from 15K+ earnings calls
Top-ranked in Construction
Ranked on what management guided this quarter
Rank buckets describe management commentary on revenue and margin. Not investment advice, and not a forecast of returns.
Fundraising & Capital Structure
See what Ashoka Buildcon Ltd said on fundraising & capital structure — free account, 30 seconds.
Order Book & Pipeline
- As of December 31, 2025, Ashoka Buildcon's balance order book stands at INR 15,927 crores.
- Including orders received post-December 31, 2025, the total order book is INR 16,235 crores.
- Roads and railway projects comprise about INR 10,292 crores (65% of total order book).
- HAM road projects: INR 1,705 crores
- EPC road projects: INR 7,025 crores
- Railway projects: INR 1,562 crores
- Power T&D projects amount to INR 5,108 crores (32.1% of total order book).
- EPC building segment constitutes INR 528 crores (3.3% of total order book).
- The entire order book is executable with appointed dates received and work in progress, except for Bowaichandi project (appointed date expected by February 2026).
2 more points from Ashoka Buildcon Ltd's call on order book
Pro opens every point from 15K+ earnings calls
Ashoka Buildcon Ltd — Quarterly revenue & net profit
Reported quarterly figures (₹ Cr). Latest (Q4 FY26): revenue ₹2.0K Cr, net profit ₹147 Cr. Revenue and profit are scaled separately — hover a quarter for exact figures.
Full financials →Continue your research
What Ashoka Buildcon's management said in earlier quarters
- Q1 FY27 earnings call analysis →
- Q2 FY26 earnings call analysis →
- Q4 FY25 earnings call analysis →
- Q1 FY26 earnings call analysis →
- Q4 FY25 earnings call →
- Q3 FY25 earnings call →
- Q2 FY25 earnings call →
- Q1 FY25 earnings call →
- Q4 FY24 earnings call →
- Q3 FY24 earnings call →
- Q2 FY24 earnings call →
- Q1 FY24 earnings call →
Arthneeti Pro · Annual
Ashoka Buildcon Ltd and 15K+ more earnings calls,
for less than your morning chai
a day
Every earnings call, ranking and concall Q&A across all four results seasons.
Secure Razorpay payment · instant access
Frequently Asked Questions
What were Ashoka Buildcon Ltd Q3 FY26 results?
For FY 2026, revenue is expected to be around 8% to 10% lower than FY 2025 due to delayed project starts and slow execution. For FY'26, revenue is expected to be approximately 8-10% lower than the previous year due to delayed project starts, with PAT showing growth due to exceptional items.
What is Ashoka Buildcon Ltd share price analysis?
Ashoka Buildcon Ltd currently shows a neutral. The stock trades at a P/E of 4.2 with a market cap of ₹3,366 Cr. Investors should review the full earnings analysis for detailed insights.
Is Ashoka Buildcon Ltd planning capital expenditure?
Q3 FY26 capex was approximately INR 15 crores.