For the current year, the company expects revenue between Rs 2,100 crores to Rs 2,200 crores. The company expects profitability to strengthen in the next year with a target top-line of Rs 2,600 to Rs 2,700 crores (Page 7).
From MBL Infrast's Q3 FY17 earnings-call transcript · updated 4 Sept 2026.
Revenue & Sales Performance
- For the current year, the company expects revenue between Rs 2,100 crores to Rs 2,200 crores.
- The top-line for the next year is anticipated to reach Rs 2,600 crores to Rs 2,700 crores.
- The company is focusing on increasing order book only after deleveraging exercises are completed.
- Growth is expected in EPC projects, with current EPC order book around Rs 1,750 crores.
- The company plans to continue bidding for EPC projects funded by NHAI, MORTH, ADB, and World Bank.
- The strategic focus includes taking hybrid annuity projects, executing, and then selling them to reduce leverage.
- Management projects margins to improve toward a target of 12% to 14% over the next couple of years.
Profitability & Margins
See what MBL Infrast said on profitability & margins — free account, 30 seconds.
Capital Expenditure Plans
- MBL Infrastructures is actively working on hybrid annuity model (HAM) projects, expecting financial closure by 31st March 2017.
- The company plans to bring financial partners into HAM projects as part of its 3-tier deleveraging strategy (including divesting operational BOT projects and replacing long-term debt).
- Discussions are ongoing with potential financial partners for strategic investments, but no definitive agreements have been signed yet; announcements will be made once funds are inducted.
- The company aims to grow specifically in EPC projects, targeting Rs 1,750 crores order book and seeking to bid aggressively in that segment.
- No specific mention of fresh capex in non-road infrastructure sectors, but there are options expected shortly in inland waterways projects.
- The general strategic direction is to focus on executing ongoing projects, de-leveraging the balance sheet, and selectively taking on new projects after consolidations and deleveraging are underway.
Fundraising & Capital Structure
See what MBL Infrast said on fundraising & capital structure — free account, 30 seconds.
Order Book & Pipeline
- As of December 31, 2016, the total order book stood at Rs 6,243.52 crores (Page 12).
- The unexecuted order book is approximately Rs 4,000 crores (Page 5).
- Of the Rs 4,000 crores unexecuted order book:
- - Around Rs 400 crores is for O&M.
- - The three remaining Hybrid Annuity Model (HAM) projects sum to about Rs 2,250 crores (Rs 1,040 crore + Rs 825 crore + Rs 458 crore) (Page 5).
- The current order book for EPC projects is about Rs 1,750 crores (Page 9).
- The company has won significant HAM projects recently, for example:
- - Four-laning of Chutmalpur to Ganeshpur & Roorkee to Gagalheri section (Rs 942 crores).
- - Four-laning of Gagalheri to Saharanpur to Yamunanagar (Rs 1,184 crores) (Page 4).
- The company is focusing on increasing order book only after deleveraging and strengthening cash flows (Page 8).
How does MBL Infrast rank vs peers in Construction?
Pro featureMBL Infrast — Quarterly revenue & net profit
Reported quarterly figures (₹ Cr). Latest: revenue ₹51 Cr, net loss ₹9 Cr. Revenue and profit are scaled separately — hover a quarter for exact figures.
Full financials →Continue your research
Frequently Asked Questions
What were MBL Infrast Q3 FY17 results?
For the current year, the company expects revenue between Rs 2,100 crores to Rs 2,200 crores. The company expects profitability to strengthen in the next year with a target top-line of Rs 2,600 to Rs 2,700 crores (Page 7).
What is MBL Infrast share price analysis?
MBL Infrast currently shows a neutral. The stock trades at a P/E of N/A with a market cap of ₹359 Cr. Investors should review the full earnings analysis for detailed insights.
Is MBL Infrast planning capital expenditure?
MBL Infrastructures is actively working on hybrid annuity model (HAM) projects, expecting financial closure by 31st March 2017.