ACME Solar Holdings commissions 160.512 MWh Battery Energy Storage System project

ACME Solar Holdings · Power

Arthneeti Research DeskPublished 1 min read

Key highlights

  • ACME Suryodaya Private Limited commissioned a 160.512 MWh BESS project in Jaisalmer, Rajasthan on July 20, 2026
  • Commercial Operation Date (COD) for the project is July 22, 2026
  • Total commissioned capacity of ACME Suryodaya Private Limited is now 285 MW / 1113.472 MWh

Why it's rated notable: The filing states commissioning of 160.512 MWh of BESS capacity by a wholly owned subsidiary with a COD of July 22, 2026, but gives no rupee value, so the level is kept at medium.

Original filing

Update On Commissioning Of Battery Energy Storage System (BESS) Project

Read the filing on BSE (PDF) →

Companies guiding to strong growth

Ranked by management's own guidance on revenue and margins — not by us.

Rossell Techsys

Aerospace & Defense

Revenue growth 40%+Margin up 2%+

Sign up free to see all 6 →

See full rankings

Rank buckets describe management commentary on revenue and margin. Not investment advice, and not a forecast of returns.

More from ACME Solar Holdings

Other capex / expansion filings this fortnight

All capex / expansion filings →

Summary written by Arthneeti from the company's filing with the stock exchange; check the original filing for full details. Arthneeti is a research and analytics platform, not a SEBI-registered investment adviser, and nothing here is a recommendation to buy or sell.