What the filing says

  • Project awarded by Bondada Engineering Limited via LOAs dated June 26, 2026, for EPC Balance of System packages for NTPC Renewable Energy's solar project in Rajasthan
  • Project value ₹740.97 crore, covering supply, services, O&M for 600 MW across two blocks, became commercially unviable due to raw material cost escalation
  • ArMee communicated inability to proceed under original terms; order book reduced by ₹740.97 crore as per SEBI Listing Regulations compliance

Original filing

Non-Execution Of The Bondada EPC Project Forming Part Of The Order Book Disclosed In The Red Herring Prospectus

Read the filing on BSE (PDF) →

Companies guiding to strong growth

Ranked by management's own guidance on revenue and margins — not by us.

Revenue growth 40%+Margin up 2%+

Sign up free to see all 6 →

See full rankings

Rank buckets describe management commentary on revenue and margin. Not investment advice, and not a forecast of returns.

More from Armee Infotech Ltd

Other order win filings this fortnight

All order win filings →

Summary written by Arthneeti from the company's filing with the stock exchange; check the original filing for full details. Arthneeti is a research and analytics platform, not a SEBI-registered investment adviser, and nothing here is a recommendation to buy or sell.