K2 Infragen Q2 Results 2026 (FY27) investor presentation: Revenue & Margins

Q2 FY27 investor presentation: what the company reported on revenue, margins and capex.

Based on K2 Infragen Ltd's Q2 FY27 investor presentation. The company has not published an earnings-call transcript for this quarter, so figures here are what the investor presentation reports, not management guidance.

Price₹41
Market cap₹51 Cr
P/E3.9

The short version

Revenue from Operations for H1-FY27: INR 626 million, a 31.1% decline YoY from INR 909 million in H1-FY26 (Page 32). EBITDA for H1-FY27: INR 13 Mn, down 90.4% YoY from INR 135 Mn in H1-FY26.

From K2 Infragen Ltd's Q2 FY27 earnings-call transcript · updated 16 Nov 2026.

How did K2 Infragen's revenue grow in the September 2026 quarter?

  • Revenue from Operations for H1-FY27: INR 626 million, a 31.1% decline YoY from INR 909 million in H1-FY26 (Page 32).
  • Operating expenses also declined by 20.8% YoY.
  • EBITDA dropped 90.4% YoY to INR 13 million in H1-FY27.
  • The unexecuted order book increased 114% to INR 9,068.83 million as of September 2026, up from INR 4,240 million in March 2026, indicating improved future revenue visibility (Page 32).

2 more points from K2 Infragen Ltd's call on revenue

Create a free account to keep reading this call

What happened to K2 Infragen's margins in Q2 FY27?

See what K2 Infragen Ltd said on profitability & margins — free account, 30 seconds.

What capex is K2 Infragen planning?

  • Power Transmission: INR 9.15 trillion capex plan by 2032 to enhance national grid and meet 458 GW peak power demand, driven by 500 GW renewable energy target by 2030 and strong policy support (Page 25).
  • Water Sector: INR 8.69 lakh crore JJM outlay extended to 2028 aiming for 100% rural coverage (81% achieved so far), supporting water infrastructure expansion (Page 26).
  • Road Infrastructure: Targeting major road projects and Hybrid Annuity Model (HAM) projects across India via JVs, with NIP targeting INR 111 trillion capex (FY20–25), 18% for roads (Page 29 & 26).
  • Renewable Energy: Expanding entry into solar and wind projects, order book INR 81.1 million with INR 76.2 million unexecuted; actively bidding for BESS projects in Rajasthan (Page 27, 21).

2 more points from K2 Infragen Ltd's call on capex

Create a free account to keep reading this call

Top-ranked in Construction

Ranked on what management guided this quarter

Guidance-ranked
Rev 1Mar 2
2Dilip Buildcon
Rev 1Mar 3
3
Rev 1Mar 3
4
Rev 1Mar 3
5
Rev 1Mar 3
Sign up free to see 3 moreTakes 30 seconds · no cardSign up

Rank buckets describe management commentary on revenue and margin. Not investment advice, and not a forecast of returns.

Is K2 Infragen raising money or cutting debt?

See what K2 Infragen Ltd said on fundraising & capital structure — free account, 30 seconds.

How big is K2 Infragen's order book?

  • The unexecuted order book as of September 2026 is INR 9,068.83 million, a 114% increase from INR 4,240 million as of March 2026. (Page 32)
  • The total project order book value is INR 11,858 million, with INR 9,069 million unexecuted. (Page 13)
  • Sectoral distribution of the order book: Roads (44.12%), Power (17.16%), Railways (37.84%), Civil Work (0.04%), Renewable Energy (0.84%). (Page 13)
  • Renewable energy segment has an order book of INR 81.1 million, with INR 76.2 million yet to be executed. (Page 20)

2 more points from K2 Infragen Ltd's call on order book

Create a free account to keep reading this call

More Q2 FY27 results in Construction

All Q2 FY27 results | Construction rankings

What K2 Infragen's management said in earlier quarters

Others in Construction this season

  • SRM Contractors (Q2 FY27)

    Revenue from operations for Q2 FY27: Rs 304 crore, up 47.09% YoY from Rs 206 crore in Q2 FY26 (Page 23, 6). Key investor presentation takeaways from SRM Contrac

  • Vishnu Prakash R (Q2 FY27)

    303.08 million or approximately 22% increase . Key results statement takeaways from Vishnu Prakash R Punglia Ltd's Q2 FY27 results statement — and how it ranks

  • Udayshivakumar (Q2 FY27)

    This represents a 122.03% increase over the previous quarter's revenue of INR 4,625.20 Lakhs. Key results statement takeaways from Udayshivakumar Infra Ltd's Q2

  • Om Infra (Q2 FY27)

    . Key results statement takeaways from Om Infra Ltd's Q2 FY27 results statement — and how it ranks against sector peers.

🔎 Who's planning the most growth?

Companies ranked by management's own guidance — revenue, margins, capex and order book, from every earnings call in India.

See rankings →

Arthneeti Pro · Annual

K2 Infragen Ltd and 15K+ more earnings calls,
for less than your morning chai

Every earnings call, ranking and concall Q&A across all four results seasons.

Secure Razorpay payment · instant access

Frequently Asked Questions

What were K2 Infragen Ltd Q2 FY27 results?

Revenue from Operations for H1-FY27: INR 626 million, a 31.1% decline YoY from INR 909 million in H1-FY26 (Page 32). EBITDA for H1-FY27: INR 13 Mn, down 90.4% YoY from INR 135 Mn in H1-FY26.

What is K2 Infragen Ltd share price analysis?

K2 Infragen Ltd currently shows a neutral. The stock trades at a P/E of 3.9 with a market cap of ₹51 Cr. Investors should review the full earnings analysis for detailed insights.

Is K2 Infragen Ltd planning capital expenditure?

Power Transmission: INR 9.15 trillion capex plan by 2032 to enhance national grid and meet 458 GW peak power demand, driven by 500 GW renewable energy target by 2030 and strong policy support (Page.