Torrent Power Q2 FY26 earnings call: Revenue & Margins

Q2 FY26 earnings call: what management said on revenue, margins and capex.

Price₹1,226
Market cap₹61.8K Cr
P/E26.6
Updated16 Oct 2026
Read4 min read

The short version

Torrent Power targets renewable capacity addition of 500 to 600 MW for the current year, with 367 MW already commissioned and the balance expected in the second half. Torrent Power reported a strong Q2 FY'26 with PBT up 42% YoY to INR 979 crores (adjusted PBT up 52%).

From Torrent Power Ltd's Q2 FY26 earnings-call transcript · updated 16 Oct 2026.

Revenue & Sales Performance

  • Torrent Power targets renewable capacity addition of 500 to 600 MW for the current year, with 367 MW already commissioned and the balance expected in the second half.
  • Most upcoming renewable capacity, except newly won projects, is expected to commission over the next 1.5 to 2 years (FY27 and first half FY28).
  • The MP Power 1.6 GW coal-based plant has a commissioning timeline of about 66 months (first unit) and 72 months (second unit) from the PPA signing, expected in the next 2 months.
  • The company is focused on expediting commissioning timelines for renewable projects.

2 more points from Torrent Power Ltd's call on revenue

Create a free account to keep reading this call

Profitability & Margins

See what Torrent Power Ltd said on profitability & margins — free account, 30 seconds.

Capital Expenditure Plans

  • Total project cost for upcoming 3 GW coal-based capacity is INR 14,000 crores.
  • Renewable CAPEX incurred in H1 FY'26 was INR 2,500 crores; total consolidated H1 FY'26 CAPEX was INR 3,700 crores.
  • Ongoing pipeline includes 3.6 GW renewable capacity, 3 GW pump storage, 1.6 GW coal plant, and 2 transmission projects.
  • Awarded BTG contract for coal plant to one of two domestic players; boiler contract under discussion.
  • FDRE Renewable Generation project of 500 MW comprising 350 MW solar, 150 MW wind, and 100 MW battery announced.

2 more points from Torrent Power Ltd's call on capex

Create a free account to keep reading this call

Top-ranked in Power

Ranked on what management guided this quarter

Guidance-ranked
1Insolation Ener
Rev 1Mar 1
Rev 1Mar 3
3
Rev 1Mar 3
4
Rev 1Mar 3
5
Rev 2Mar 3
Sign up free to see 3 moreTakes 30 seconds · no cardSign up

Rank buckets describe management commentary on revenue and margin. Not investment advice, and not a forecast of returns.

Fundraising & Capital Structure

See what Torrent Power Ltd said on fundraising & capital structure — free account, 30 seconds.

Order Book & Pipeline

  • The pipeline projects as of September 30, 2025, include:
  • 3.6 gigawatt renewable capacity
  • 3 gigawatt pump storage capacity
  • 1.6 gigawatt coal plant
  • 2 transmission projects at Khavda and Solapur
  • A 1.6-gigawatt coal-based power plant project secured LOA from MP Power Management Company Limited.
  • A 500 megawatt FDRE renewable generation project (solar, wind, battery mix) has been awarded from TPLD.

2 more points from Torrent Power Ltd's call on order book

Create a free account to keep reading this call

Torrent Power Ltd — Quarterly revenue & net profit

Revenue Net profit
Dec 2024Q3 FY25
Mar 2025Q4 FY25
Jun 2025Q1 FY26
Sep 2025Q2 FY26
Dec 2025Q3 FY26
Mar 2026Q4 FY26

Reported quarterly figures (₹ Cr). Latest (Q4 FY26): revenue ₹6.4K Cr, net profit ₹331 Cr. Revenue and profit are scaled separately — hover a quarter for exact figures.

Full financials →

Others in Power this season

  • Reliance Infrastructure Ltd (Q2 FY26)

    Revenue: ₹12,345 Crore . Key investor presentation takeaways from Reliance Infrastructure Ltd's Q2 FY26 investor presentation — and how it ranks against sector

  • Reliance Power (Q2 FY26)

    Revenue for H1 FY26: ₹8,257 crore . Key investor presentation takeaways from Reliance Power Ltd's Q2 FY26 investor presentation — and how it ranks against secto

  • GMR Urban (Q2 FY26)

    Consolidated Total Income: INR 19.2bn, up 28% YoY and 9% QoQ (Page 10). Key investor presentation takeaways from GMR Power & Urban Infra Ltd's Q2 FY26 investor

  • Adani Energy Solutions Ltd (Q2 FY26)

    Distribution business capex around INR 1,500-1,600 crores, translating to INR 250-275 crores EBITDA. Key concall takeaways from Adani Energy Solutions Ltd's Q2…

🔎 Who's planning the most growth?

Companies ranked by management's own guidance — revenue, margins, capex and order book, from every earnings call in India.

See rankings →

Arthneeti Pro · Annual

Torrent Power Ltd and 15K+ more earnings calls,
for less than your morning chai

a day

Every earnings call, ranking and concall Q&A across all four results seasons.

Secure Razorpay payment · instant access

Frequently Asked Questions

What were Torrent Power Ltd Q2 FY26 results?

Torrent Power targets renewable capacity addition of 500 to 600 MW for the current year, with 367 MW already commissioned and the balance expected in the second half. Torrent Power reported a strong Q2 FY'26 with PBT up 42% YoY to INR 979 crores (adjusted PBT up 52%).

What is Torrent Power Ltd share price analysis?

Torrent Power Ltd currently shows a neutral. The stock trades at a P/E of 26.6 with a market cap of ₹61,774 Cr. Investors should review the full earnings analysis for detailed insights.

Is Torrent Power Ltd planning capital expenditure?

Total project cost for upcoming 3 GW coal-based capacity is INR 14,000 crores.

Keep Torrent Power Ltd on your radar — track it to get its next earnings analysis in your feed.

This analysis is AI-generated based on publicly available earnings data and the company's earnings call transcript. This is not investment advice. Please consult a SEBI-registered advisor before making investment decisions.