Torrent Power Ltd
Torrent Power Ltd Q3 FY26 Results & Concall Highlights: Revenue, Margins & Order Book
Q3 FY26 earnings call: what management guided on revenue, margins and order book.
The short version
Power demand is expected to grow inline with GDP at around 5-6% next year after a current aberration due to extended monsoons and high base last year (Page 6). Torrent Power expects growth driven by commissioning of ~1.2-1.5 GW renewable capacity annually over the next two years, supporting revenue and profit.
From Torrent Power Ltd's Q3 FY26 earnings-call transcript · updated 23 Aug 2026.
Revenue & Sales Performance
- Power demand is expected to grow inline with GDP at around 5-6% next year after a current aberration due to extended monsoons and high base last year (Page 6).
- Renewable capacity addition will pick up with commissioning of about 1.2 to 1.5 gigawatt in FY 2027 and similar pace anticipated for following years (Page 5, 8).
- The company aims to reach 10 gigawatts of renewable capacity, actively bidding for projects with a threshold IRR and locking in capacities when commercials are favorable (Page 8).
2 more points management made on revenue & sales performance
Profitability & Margins
See what Torrent Power Ltd said on profitability & margins — free account, 30 seconds.
Capital Expenditure Plans
- Cumulative capex in first 9 months of FY '26:
- Licensee and franchisee: ~INR 1,100 crores
- Transmission (coal project): ~INR 400 crores
- Pumped Storage Project (PSP): ~INR 300 crores
- Renewable energy: ~INR 3,100 crores (noted pickup in Q3 capex INR 1,750 crores)
- No specific capex target given for entire FY '26; Q3 run rate expected to continue.
- Renewable commissioning target: 1.2 to 1.5 GW in FY '27, similar pace in following years.
- Pipeline includes 4 GW renewable, 3 GW pumped storage, 1.6 GW coal, and transmission projects at Khavda and Solapur.
- Focus on maintaining financial discipline with comfortable leverage (net debt-to-equity 0.40 as of March '25).
2 more points management made on capital expenditure plans
Top-ranked in Power
Ranked on what management guided this quarter
Rank buckets describe management commentary on revenue and margin. Not investment advice, and not a forecast of returns.
Fundraising & Capital Structure
See what Torrent Power Ltd said on fundraising & capital structure — free account, 30 seconds.
Order Book & Pipeline
2 more points management made on order book & pipeline
Torrent Power Ltd — Quarterly revenue & net profit
Reported quarterly figures (₹ Cr). Latest: revenue ₹6.4K Cr, net profit ₹331 Cr. Revenue and profit are scaled separately — hover a quarter for exact figures.
Full financials →Continue your research
What Torrent Power Ltd's management said in earlier quarters
Others in Power this season
- Adani Energy Solutions Ltd (Q3 FY26)
Smart meter installations have crossed 92 lakh meters, with plans to complete balance meters (~1 crore total) in the next 12 months, ensuring strong revenue…
- JSW Energy Ltd (Q3 FY26)
Power sales grew sharply by 65% YoY in Q3 FY26, reaching 11.1 billion units; 9-month generation up 62% YoY to 39.6 billion units. Key concall takeaways from…
- Adani Green Energy Ltd (Q3 FY26)
Strategy includes maintaining ~20% merchant capacity, utilizing infirm power, and monetizing flexibility through battery storage to capture peak pricing…
- IndiGrid Trust (Q3 FY26)
INR7,500 crores, growing AUM from INR32,000 crores to about INR40,000 crores. Key concall takeaways from IndiGrid Infrastructure Trust's Q3 FY26 earnings call…
Frequently Asked Questions
What were Torrent Power Ltd Q3 FY26 results?
Power demand is expected to grow inline with GDP at around 5-6% next year after a current aberration due to extended monsoons and high base last year (Page 6). Torrent Power expects growth driven by commissioning of ~1.2-1.5 GW renewable capacity annually over the next two years, supporting revenue and profit.
What is Torrent Power Ltd share price analysis?
Torrent Power Ltd currently shows a neutral. The stock trades at a P/E of 28.7 with a market cap of ₹66,692 Cr. Investors should review the full earnings analysis for detailed insights.
Is Torrent Power Ltd planning capital expenditure?
Cumulative capex in first 9 months of FY '26: - Licensee and franchisee: ~INR 1,100 crores - Transmission (coal project): ~INR 400 crores - Pumped Storage Project (PSP): ~INR 300 crores - Renewable energy: ~INR 3,100 crores (noted pickup in Q3 capex INR 1,750 crores) - No specific capex target given for entire FY '26; Q3 run rate expected to continue.