ACME Solar Holdings commissions additional 52.32 MW / 209.28 MWh BESS at Rajasthan project

ACME Solar Holdings · Power

Arthneeti Research DeskPublished 1 min read

Key highlights

  • Commissioned 52.32 MW / 209.28 MWh Battery Energy Storage System on Nov 17, 2026
  • Project located at Kelan Village, Chhatargarh Tehsil, Bikaner, Rajasthan, part of 300 MW / 1200 MWh FDRE Project
  • Total commissioned BESS capacity now 247.67 MW / 990.68 MWh with PPA signed with SJVN Limited

Original filing

Update On Commissioning Of Battery Energy Storage System (BESS) Project

Read the filing on BSE (PDF) →

Companies guiding to strong growth

Ranked by management's own guidance on revenue and margins — not by us.

Knowledge Marine

Engineering Services

Revenue growth 40%+Margin up 2%+

Sign up free to see all 6 →

See full rankings

Rank buckets describe management commentary on revenue and margin. Not investment advice, and not a forecast of returns.

More from ACME Solar Holdings

Other capex / expansion filings this fortnight

All capex / expansion filings →

Summary written by Arthneeti from the company's filing with the stock exchange; check the original filing for full details. Arthneeti is a research and analytics platform, not a SEBI-registered investment adviser, and nothing here is a recommendation to buy or sell.