Sambhv Steel Q4 FY26 Earnings Analysis
Published 18 Aug 2026 | Industrial Products | Market Cap: ₹3.6K Cr
Price
₹120
Market Cap
₹3.6K Cr
P/E Ratio
21.4
Earnings Summary
Sambhv Steel Tubes aims to reach a finished steel capacity of 2 million tons by 2030. Volume growth expected around 10% to 15% in FY27 compared to FY26.
📊 Revenue & Sales Performance
- →Sambhv Steel Tubes aims to reach a finished steel capacity of 2 million tons by 2030.
- →Product mix target for 2030: 10 lakh tons MS pipes and tubes, 3 lakh tons coated steel, 7 lakh tons stainless steel.
- →Capacity utilization expected around 60% by 2030.
- →Volume growth expectation: 37% growth recently, capacity doubling with expansions by FY28.
- →Expansion phases: Phase 1 (3,60,000 tons stainless steel coil capacity) commissioning by Q4 FY27; Phase 2 and 3 timelines to be announced post Phase 1 utilization.
- →Revenue growth: 60% increase recorded recently; new capacities and product lines expected to significantly increase revenue.
- →EBITDA per ton guidance: INR 7,500-8,000 for Q1 FY27; expected sustained EBITDA margin around 10-12%.
- →Market share goal: 10-12% in MS coil & pipe and stainless steel flat product segments by 2030.
📈 Profitability & Margins
- →Volume growth expected around 10% to 15% in FY27 compared to FY26.
- →EBITDA per ton guidance for Q1 FY27 is INR 7,500 to INR 8,000; sustainable range expected around INR 7,000 to INR 8,000.
- →EBITDA margin expected to remain steady around 10% to 12%, with 10% as a bare minimum in a bear scenario.
- →PAT margin operating bandwidth is 5% ±1%; worst-case 4%, best-case 6%.
- →Revenue growth supported by increased production capacities and market expansion.
- →Expansion projects (Greenfield Kesda plant, ERW capacity increase, power plant) expected to drive scale and profitability improvements post FY28.
- →Long-term goal of ~2 million tons installed capacity by 2030, targeting 10-12% market share in both MS pipes/tubes and stainless steel coils.
- →Continued focus on value-added high-margin products and operational efficiencies to support earnings growth.
🏗️ Capital Expenditure Plans
- →Current capex announced: INR 930 crores; INR 300 crores already spent, balance INR 630 crores to be incurred.
- →Additional capex of INR 200 crores announced for debottlenecking and operational efficiency, including power plant and pipe mill upgrades.
- →Peak long-term debt planned around INR 800 crores; INR 200-300 crores for working capital.
- →Key projects:
- → - Kesda Greenfield expansion: 1.2 million ton finished product capacity; Phase 1 (360,000 tons stainless steel coil) commissioning by Q4 FY 2027.
- → - Captive power plants: 30 MW Sarora plant (self-sufficient power) and 25 MW Kesda plant for phase 1.
- → - Debottlenecking of existing rolling mill (additional 150,000 ton/year capacity).
- → - ERW expansion through DFT route with INR 50 crores capex unlocking INR 40-50 crores operating value.
- →Phase 2 and 3 expansions planned post Phase 1 utilization review; product mix and timelines to be announced later.
💰 Fundraising & Capital Structure
- →Sambhv Steel Tubes plans to fund its expansion primarily through debt, with no immediate mention of equity fundraising.
- →For the Kesda capex (INR930 crores total), around INR675 crores of term loan (debt) is planned.
- →Additional INR200 crores capex announced this quarter will be funded through a mix of internal accruals and debt, with a maximum INR150 crores debt.
- →Management is prudent about debt, targeting long-term debt not exceeding 1.5 times net worth or forward EBITDA.
- →No current plans for further equity raises; focus is on balancing debt with internal accruals.
- →Future capex beyond Phase 1 (e.g., Phase 2 and 3) is not finalized, so further fundraising plans will be announced later.
📋 Order Book & Pipeline
Key Metrics
Frequently Asked Questions
What were Sambhv Steel Q4 FY26 results?
Sambhv Steel Tubes aims to reach a finished steel capacity of 2 million tons by 2030. Volume growth expected around 10% to 15% in FY27 compared to FY26.
What is Sambhv Steel share price analysis?
Sambhv Steel currently shows a neutral. The stock trades at a P/E of 21.4 with a market cap of ₹3,567 Cr. Investors should review the full earnings analysis for detailed insights.
Is Sambhv Steel planning capital expenditure?
Current capex announced: INR 930 crores; INR 300 crores already spent, balance INR 630 crores to be incurred.
This analysis is AI-generated based on publicly available earnings data and concall transcripts. This is not investment advice. Please consult a SEBI-registered advisor before making investment decisions.